a
Thursday, 03-Jul-2008 23:53:54 UTC
TCV College for Higher Studies at Bangalore-Under Construction
tcv college map tcv college staff quarter sept 2007

In view of the urgency of the project we are pleased to report construction work on phase - I is going on full swing. The first phase of the construction work has begun and is making good progress at this time. With the construction work of the classrooms block, hostels and staff quarters already started, we are looking forward to a smooth progress in the months ahead. We would like to express our deepest gratitude to all donors who have supported and generously contributed toward this project. Since there is further need for funding for this project, your continued support and solidarity would be most helpful and appreciated. This is by far the most urgent project as the need of the hour for our community.

Updates of the Current Project:
  • Classrooms with Administrative & Seminar Rooms (I Phase)
  • Girl Hostel (I Phase)
  • Staff Quarter (I Phase)
  • Play Ground
  • Visiting Professor's Quarter
  • Mess & Canteen
  • Road & Landscaping
1. Classrooms:
(a) Right Wing (20 Classrooms):
  • Structural & Concrete Work upto 3rd Floor (15 Classrooms)
  • Internal Plastering of 2nd Floor Completed (10 Classrooms)

  • (b) Staffroom & 2 Seminar Rooms:
  • Structural Work upto 2nd Floor Completed
  • Second floor column work under progress

  • (c) Left Wing (15 Classrooms):
  • Foundation work completed
  • Ground Floor Concrete Block Masonry, Column Works & Slab Casting Completed
  • First Floor Concrete Block Masonry & Column Works under Progress

  • 2. Girl Hostel:
    (a) Block-A (70 Rooms):
  • Structural and Concrete Work Completed up to 4th Floor
  • Internal Plastering Work upto 4th Floor Completed
  • Kota Stone Flooring Work is 80% Completed

  • (b) Block-B (61 Rooms):
  • Structural and Concrete Work upto 2nd Floor Completed
  • Third Floor Steel Work is in Progress

  • 3. Staff Quarter (16 Family Qaurters):
  • Structural, Concrete and Internal Plastering Completed
  • External Plastering 75% done & Stone Cladding Work is in Progress

  • 4. Play Ground: Site Excavation Work 90% Completed

    5. Visiting Professor’s Quarter:Site plotting is done and foundation soil excavation is in progress

    6. Mess & Canteen: Site plotting is done but site visit and the final approval from the architect is waited.

    7. Road & Landscaping: After the 12 days of site survey done by Mr. Nakahara (landscaping architect) we were able to start with the Land clearance and check dam work, it is in progress with the grass plantation.

    8. Library Block:Site problem and needs discussion.

    9. Ext. Development:
  • (a) Shifting of the HT electric poles from the center of the classrooms area is completed.
  • (b) Transformer and permanent electric connection is in progress.
  • (c) Registration of the co-operative is in under process.
  • Furthermore, recently we revamped the construction team to strengthen it administratively with inclusion of more experienced technical people in the field to further enhance the performance. The first batch of students is expected in July 2008. As such, we are fully confident that our construction team will go all out to meet the desired objective. Simultaneously, necessary academic planning and other related matters are also being pursued vigorously, not to mention the all important fund-raising. We are truly grateful to each and everyone who enabled us to reach thus far with your generous contributions. As there is still the need for more funding, we hope you will come forward to assist us with funding support in the realization of this critical project for the youth - who are our future.

    Thank you very much for the interest and understanding. Updates of the project will be available on time to time basis through our Half Yearly Metok Magazine and other information outlets of TCV.

    Project Manager
    TCV College for Higher Studies
    Mysore Road, Hejjala Post
    Ramnagar Distt., Bangalore Rural-562109 Karnataka (India)

    Tel: 080 28437267 | Fax: 080 28437266

    ♣ tcvcollege (at) gmail.com (Construction)
    ♣ teamtcv(at)gmail.com (Principal)
    ♣ headoffice(at)tcv.org.in


    TCV COLLEGE PICTURE UPDATES


    TCV College Brochure 




    Search