The Dalai Lama Insitute for Higher Education-Bangalore (Under Construction)
tcv college map tcv college staff quarter sept 2007

We recently revamped the construction team to strengthen it administratively with inclusion of more experienced technical people in the field to further enhance the performance. We are truly grateful to each and everyone who enabled us to reach this far with your generous contributions. As there is still the need for more funding, we hope you will come forward to assist us with funding support in the realization of this critical project for the youth - who are our future.

CONSTRUCTION PROJECT STATUS-Progress Report (July 2009)
    PHASE-I:
  • 1. Class rooms, Staff rooms with Seminar hall & Administrative block
  • 2. Girls Hostel
  • 3. Staff Quarters
  • 4. Community Center
  • 5. Visiting Professor's Hostel

A brief description on the construction work of each block is as under:

    1. CLASS ROOM BLOCK:
  • RCC Frame structure is completed for both sides of the Class room wing
  • Entire internal plastering work is completed for both sides of the Class room wing
  • External platering work nad vitrified tile flooring work is under progress for 1 wing
  • RCC frame structure for the Staff block (Central Wing) is completed upto 3rd floor except roof truss work if the Seminar hall
  • Painting work is under progress

Overall 80% of the total work is completed

    2. GIRLS HOSTEL-A BLOCK:
  • RCC frame structure is completed.
  • Entire finishing work of rooms inside and outside is completed with bathrooms
  • Stone cladding work is completed
  • Plastering work for side rooms and the wash area is under progress

Overall 98% of the total work is completed.

    GIRLS HOSTEL-B BLOCK:
  • RCC frame structure is completed
  • Internal plastering work is completed except bathrooms
  • Entire flooring work, external plastering, painting and plumbling work are under progress

Overall 78% of the total work is completed.

    3. STAFF QUARTERS:
  • RCC Frame structure with plastering work, stone cladding work, sanitary, sewerage and electrical works are completed
  • All the 16 Staff quarters are completed
  • External land development with drawing system are completed
  • Kota stone polishing work is in progress

Overall 99.5% of the total work is completed.

    4. COMMUNITY CENTER:
  • Foundation and slab work are completed upto first floor
  • Concrete block masonry is under progress on the first floor
  • Ground floor roof truss work, flooring, plastering, plumbing and painting work of the dining area are completed

Overall 78% of the total work is completed.

    5. VISITING PROFESSORS' BLOCK:
  • RCC frame structure is completed
  • Internal and external plastering work is under progress
  • Plumbing work is under progress

Overall 75% of the total work is completed.

    EXTERNAL DEVELOPMENTS:
  • Construction of 3 of check dams have been completed and 4th is under progress
  • Landscaping work including grass and tree plantation are under progress
  • Leveling of playground is under progress (90% Completed)
  • Grass plantation and area development around the community center is under progress
    CONCLUSION:
  • With firm conviction that the college will play a vital role in providing a meaningful education to our youths, we take this opportunity to thank each and every individual for the continued generosity and most valuable support toward this project.
  • Thank you very much for the interest and understanding. Updates of the project will be available on time to time basis through our Half Yearly Metok Magazine and other information outlets of TCV.

Principal (Academic) | Project (Construction)
The Dalai Lama Insitute for Higher Education
Mysore Road, Hejjala Post
Ramnagar Distt., Bangalore Rural-562109 Karnataka (India)

Tel: 080 28437267 | Fax: 080 28437266

♣ tcvcollege (at) gmail.com (Principal)
♣ nawangdorjee(at)gmail.com (Construction)
♣ headoffice(at)tcv.org.in


TCV COLLEGE PICTURE UPDATES

TCV COLLEGE-INAUGURATION PICTURES



Search